Installation of AWTP-(2) 1000 Hp Reservoir Vertical Turbine RFP
Posted
Oct 2, 2026
Nov 17, 2026
Installation (replacement) of two (2) 1000 HP motors at the water treatment plant reservoir pump station. Winning bidder must provide, install and laser-align the motors. Installation will include providing a crane, removing and replacing the pump house roof, existing motor removal and transport to on-site storage location, providing provisions for vibration detectors 90 degrees apart with ¼-28 UNF tapped hole to mount our sensors, providing (and laser aligning shafts) a new coupling for each unit, making all electrical disconnections and reconnections, installing a vibration system (and ensuring proper operation), performing vibration analysis before and after new motor installation, and all other tasks, requirements, and specifications outlined in the contract documents.